Takt Time Calculator

Takt time is available production time divided by customer demand. Enter the time you have and the units required to see the target time per unit and the hourly rate it implies.

Net of breaks, meetings and planned maintenance.

units

Units required in that available time.

Definitions of downtime, planned time and good output vary between plants. Use the same definitions every time so results stay comparable.

Worked example

Inputs: Available production time = 450 · Time unit = minutes · Customer demand = 900

Takt time
30 sec per unit
Takt time (minutes)
0.5 min per unit
Required rate
120 units per hour

Formula

  • Takt time = Available production time ÷ Customer demand
  • Required rate (units per hour) = Customer demand ÷ Available hours

Calculation information

Assumptions

  • Available time already excludes breaks, planned maintenance and meetings.
  • Demand is the quantity you must complete in that same period.

Rounding

Shown to 2 decimal places (3 for minutes).

Limitations

  • Takt time is a demand-driven target, not what your line can do — compare it with your actual cycle time.
  • It assumes steady demand across the period.

Last reviewed 2026-11-15.

Frequently asked questions

What is takt time?

The rate at which you need to complete a unit to meet customer demand: available production time divided by demand.

What is the difference between takt time and cycle time?

Takt time is set by demand; cycle time is how long your process actually takes per unit. If cycle time is longer than takt time, you can't meet demand without changes.