OEE Calculator

Enter planned production time, downtime, ideal cycle time and the good and total counts. The tool shows availability, performance, quality and the OEE they multiply to.

min

Scheduled run time, excluding planned breaks.

min

Unplanned stops plus changeovers and setup, if you count them.

The fastest time per unit the machine can sustain.

Good and defective.

Definitions of downtime, planned time and good output vary between plants. Use the same definitions every time so results stay comparable.

Worked example

Inputs: Planned production time = 480 · Downtime = 60 · Ideal cycle time = 0.5 · Cycle time unit = minutes per unit · Total units produced = 700 · Good units = 665

Run time
420 min
Availability
87.5%
Performance
83.33%
Quality
95%
OEE
69.27%

Formula

  • Run time = Planned production time − Downtime
  • Availability = Run time ÷ Planned production time
  • Performance = (Ideal cycle time × Total units) ÷ Run time
  • Quality = Good units ÷ Total units
  • OEE = Availability × Performance × Quality

Calculation information

Assumptions

  • Planned production time excludes planned breaks and idle time you chose not to schedule.
  • Downtime is time the machine was not running when it should have been.
  • Rework counts as not good unless you decide otherwise.

Rounding

Percentages shown to 2 decimal places; OEE uses the unrounded factors.

Limitations

  • OEE definitions vary slightly between plants. Use the same definitions each time so results stay comparable.

Last reviewed 2026-11-15.

Frequently asked questions

What is a good OEE?

It depends on the process. Compare against your own history first, then against similar lines — not a single universal number.

Does OEE equal good units × ideal cycle time ÷ planned time?

Yes. The three factors cancel down to that, which is a handy cross-check.