Raw Material Requirement Calculator

Enter the planned output and how much material each unit uses. Add a wastage allowance and your stock on hand to see what you still need to buy.

units
%

Definitions of downtime, planned time and good output vary between plants. Use the same definitions every time so results stay comparable.

Worked example

Inputs: Planned production = 8000 · Material per unit = 0.35 · Wastage allowance = 3 · Stock on hand = 2500 · Material unit = kg

Net requirement
2,800 kg
Gross requirement (with wastage)
2,884 kg
Stock on hand
2,500 kg
Shortfall to order
384 kg

Formula

  • Net requirement = Planned production × Material per unit
  • Gross requirement = Net requirement × (1 + Wastage ÷ 100)
  • Shortfall = Gross requirement − Stock on hand

Calculation information

Assumptions

  • Wastage is a percentage added on top of the net requirement.
  • All quantities share the unit you select.

Rounding

Quantities shown to 3 decimal places.

Limitations

  • Doesn't consider lead times, minimum order quantities or stock already reserved.

Last reviewed 2026-11-15.

Frequently asked questions

Is wastage taken off the gross or added to the net?

Added to the net requirement. A 3% allowance on 100 kg gives 103 kg, not 100 ÷ 0.97.

Related data tools

Free lookups from open public data that go with this kind of work.

All Manufacturing & Industry data tools →